Scheduled Paving
July 9, 2025
On July 14th (weather permitting), Pavecon Construction is scheduled to begin paving repair work at the intersection of Prairie Ridge and Hickory Falls. The duration of the project is expected to be approximately 14 days.
That duration could be extended if significant subsurface damage is discovered during the removal of the existing damaged concrete. If you have any questions, please feel free to contact us https://www.canyonfallsmud.com/contacthere.https://www.canyonfallsmud.com/contact
below is a timeline of the repairs.
Monday July 14th: Demo sawcut of the areas.
Tuesday July 15 – Wednesday July 16th: Concrete Demo and Pour of the Sidewalk and first half of the split pour in the intersection.
Monday July 21 – Tuesday July 22nd: Complete 2nd half of the split pour in the intersection, and repair damaged curb area.
Monday July 28th: Joint Seal and Removal of Barricades
Thank you in advance for your patience while we complete this.